Skip to main content

First and Boundary Pump Station Upgrades

Location Burnaby, BC, Canada
Owner City of Burnaby
Engineer Kerr Wood Leidal Associates Ltd.
Status Completed Jun 2016

The scope of this project consisted of demolition of the exiting pump station, installation of a new 1500mm manhole and rehabilitating the existing wet and dry wells converting the dry well into a second wet well. Under this contract was a new control building and installation of all electrical equipment. A new underground valve chamber was installed including all mechanical & civil piping, fittings and appurtenances. Construction took place on a very small lot at a very busy intersection with very little disruption and no damage to neighbouring business that were in a very close proximity.