Enderby I.R. No. 2 Domestic Water System Improvements
This project began in January 2017 and was completed by January 2018. Construction included a new water treatment plant that houses Chemical Feed Equipment, Manganese Removal Equipment and Template Assisted Crystallization vessels and all associated piping, process valves and appurtenances. A new cast-in-place concrete reservoir was also constructed along with 6km of HDPE pipe consisting of sizes from 100mm to 250mm. 4 well upgrades were undertaken and 2 new PRV stations were installed.